NEC
Birmingham
Comprehensive Wall Cladding Refurbishment
The NEC in Birmingham is one of Europe’s premier event venues, hosting over 500 events annually and welcoming around 2.4 million visitors each year.
Originally constructed in 1976, sections of the NEC’s external cladding had become visibly aged, with peeling coatings and declining aesthetic quality. Roofclad Systems was appointed to deliver a comprehensive wall cladding refurbishment across multiple rear-of-house elevations, which included Halls 3A, 4, 5 and the Gardens.
The objective was clear: enhance visual appeal, protect the existing structure, and deliver a cost-effective solution with a substantial lifespan.
The project presented several technical and logistical challenges:
In addition, careful drilling and fixing methods were essential to ensure safe handling of the existing material while maintaining structural integrity.
Roofclad Systems implemented a fully compliant overcladding solution, designed to encapsulate the existing substrate and minimise disturbance:
A new single-skin profiled metal cladding system was installed, using support rails fixed directly to the existing façade.
Key elements included:
Where obstructions remained, bespoke solutions such as duct extensions and tailored panel adjustments ensured a precise fit and clean finish.
The completed project delivered a significant visual transformation while enhancing durability and protection:
“Roofclad Systems delivered a high-quality cladding solution that has significantly improved the appearance of our facilities while meeting all safety and compliance requirements. The team managed the complexities of the project professionally, ensuring minimal disruption throughout.”
– Steven Willis, NEC Group