Heathcote Fabrics - Roofclad
menu close icon

Heathcote Fabrics

Client

Heathcote Fabrics

Location

Tiverton, Devon

Specification of Work

Strip & Resheet, Asbestos Solutions, Rooflight Solutions, Guttering Solutions

Project Length

Two weeks (aligned with factory shutdown)

The Project

Heathcote Fabrics commissioned Roofclad Systems to replace the roof of their Tiverton facility. The project was scheduled to align with the factory’s annual two-week shutdown, ensuring production was not impacted.

Client Problems

  • Strict timeframes required all work to be completed within the shutdown period.
  • Existing roof and northern light glazing needed removal and replacement without damaging production equipment.
  • The project required safe handling of asbestos-containing materials.

Our Solution

  • Installed fully boarded external walkway scaffolding with safety netting for internal operative protection and two-layer debris netting to safeguard machinery.
  • Stripped and replaced an average of 200m² of roof and glazing per day with new composite panel and polycarbonate system.
  • Completed internal clean-down after each phase.
  • Handed the building back to the client with 24 hours to spare, allowing production to resume on schedule.
  • Returned the following year to complete another phase of replacement roofing.

Interested in how we can help you?

Speak to our trusted team today.